How Much Does a Commercial Kitchen Cost in India?

Home › Commercial Kitchen Contractor › Cost in India

Real per-square-foot ranges by kitchen tier, a line-item worked budget, and the costs that quietly appear after the quote is signed.

A commercial kitchen cost in India is the first number a buyer asks for and the last one any contractor can give honestly without first knowing equipment tier, covers-per-hour target, and site condition. This page gives the real ranges. More usefully, it explains why two kitchens of identical floor area land at very different final numbers — which is the knowledge that actually helps once you are comparing quotes rather than estimating. It is one part of our wider guide to working with a commercial kitchen contractor in India.

Everything below assumes you already know what sits inside a contractor’s scope. If you do not, start with what a commercial kitchen contractor does, then come back.

Commercial kitchen cost planning and budget calculation

What are the typical cost ranges by kitchen tier?

Commercial kitchen contracting in India typically runs ₹1,800–₹4,500 per square foot, with standard QSR-format kitchens at the lower end and premium hotel kitchens carrying imported equipment and complex ventilation at the upper end. Equipment specification drives most of the variance, not floor area.

Kitchen tierTypical range (per sq ft)Where it applies
Standard / QSR₹1,800 – ₹2,500Fixed-menu, high-turnover kitchens with domestic equipment
Mid-tier restaurant / hotel outlet₹2,500 – ₹3,500Mixed domestic and imported equipment, moderate MEP complexity
Premium hotel / large-format₹3,500 – ₹4,500+Imported combi ovens, extensive ventilation, multi-section kitchens

These assume a reasonably standard site — existing structural shell, accessible utility connections, no major demolition. A retrofit inside a constrained basement, or a kitchen needing new structural openings for ventilation risers, moves cost up independent of equipment tier.

Treat a per-square-foot figure as a sanity check, never as a budget. A 1,200 sq ft kitchen serving grilled sandwiches and one serving a full Indian, Continental and tandoor menu occupy the same area and differ by a factor of two or more. The menu sets the equipment list; the equipment list sets the cost.

What are the main cost heads in a commercial kitchen project?

Five heads account for a commercial kitchen budget: equipment supply at 50–65% of value, stainless steel fabrication at 15–25%, ventilation and exhaust at 10–18%, installation and labour at 8–15%, and project management with commissioning at 5–10%.

Knowing this split is what lets you read a quotation properly. When a competing bid lands 20% lower, the gap sits in one of these heads — and it is almost always equipment specification or stainless grade.

Cost headShare of valueWhat drives it upWhat drives it down
Equipment supply50–65%Imported brands, high capacity, premium specificationDomestic manufacture, right-sized capacity
Stainless steel fabrication15–25%SS 304 throughout, heavier gauge, complex shapesStandard modules, simpler detailing
Ventilation and exhaust10–18%High extraction volume, long duct runs, terrace worksCompact layout, short duct route
Installation and labour8–15%Difficult access, upper floors, phased workingClear site, single mobilisation
Project management5–10%Long programme, multi-phase handoverCompressed single-phase delivery

Ventilation is the head buyers most consistently underestimate, because they think of it as building services rather than kitchen scope. Owners budget for the hood and forget the duct run, the fan, the make-up air unit, the terrace platform and the acoustic treatment. On a hotel kitchen with a long vertical riser, ventilation alone can approach the cost of the entire cooking line. The technical basis is in commercial kitchen ventilation design, and the pressure-balance requirement in commercial kitchen make-up air systems.

What does commercial kitchen equipment cost by category?

Within the equipment head, cooking typically consumes 30–40%, refrigeration 25–35%, warewashing 10–18%, and preparation equipment 6–12%. Indicative mid-tier price bands sit below — ranges are wide because origin and capacity move each line substantially.

EquipmentIndicative rangeNote
Four to six burner range with oven₹85,000 – ₹2,80,000Domestic to European manufacture
Combi oven, 6 grid₹3,50,000 – ₹7,50,000Injection steam cheaper than boiler-based
Combi oven, 10 grid₹5,00,000 – ₹11,00,000The single largest line in most mid-tier kitchens
Chinese range, 2 burner₹1,40,000 – ₹2,60,000
Tandoor with exhaust provision₹85,000 – ₹1,80,000
Two-tank fryer₹65,000 – ₹2,20,000Built-in filtration adds materially
Griddle or salamander₹45,000 – ₹1,60,000
Walk-in cold room, 8 sq m₹3,50,000 – ₹6,50,000Panel thickness and temperature drive the range
Undercounter chiller, 2 door₹70,000 – ₹1,40,000
Upright freezer, 2 door₹95,000 – ₹1,90,000
Ice machine, 100 kg/day₹1,20,000 – ₹2,60,000
Hood-type dishwasher₹2,60,000 – ₹5,50,000
Planetary mixer, 20 litre₹65,000 – ₹1,60,000
Exhaust hood, per running metre₹18,000 – ₹45,000Filtration type drives the range

The spread inside each row is real and not arbitrary. A European combi oven at two to three times an Indian equivalent typically delivers tighter temperature and humidity control, lower energy per cover, longer service life, and a parts chain that exists for a decade. Whether that premium returns depends entirely on utilisation — a unit running four cycles a day repays it; one running a single cycle does not. The comparison is worked through in imported versus Indian commercial kitchen equipment, and selection logic in choosing the right commercial kitchen equipment.

Where you buy matters as much as what you buy. An authorised dealer registers warranty to you and gives you an obligated service network; a trader selling parallel stock gives you a lower invoice and a warranty that lasts as long as the trader does — see authorised dealer versus distributor versus trader.

What does stainless steel fabrication cost?

Fabrication runs roughly ₹1,100–₹2,800 per square foot of fabricated surface, driven by grade, gauge and complexity. SS 304 at 1.2 mm is the working standard for food-contact surfaces. SS 202 costs 25–35% less and fails considerably sooner in wet areas.

This is the easiest place in a quotation for a contractor to cut invisibly, and the most expensive place for you to save.

Grade. SS 304 is austenitic, with roughly 18% chromium and 8% nickel. The nickel is what resists the chlorides in cleaning chemicals, salt and humidity. SS 202 substitutes manganese and nitrogen for most of the nickel. On delivery day the two are indistinguishable. In a dishwash area, SS 202 pits and stains within 18 to 24 months. SS 430 is ferritic with no nickel and belongs on non-food-contact cladding at most.

Gauge. A 1.2 mm worktop takes heavy prep without deflection. At 0.8 mm it drums under a knife, dents under a stockpot and telegraphs every fixing point. The saving is a few hundred rupees per square foot against a surface you will replace inside five years.

ItemIndicative range
Work table with undershelf, per running foot₹4,000 – ₹7,500
Sink unit, single bowl with drainboard₹16,000 – ₹38,000
Wall shelf, per running foot₹1,600 – ₹3,400
Pot rack, per running foot₹2,200 – ₹5,000
Dish landing table with pre-rinse₹30,000 – ₹75,000
Trolley, general purpose₹10,000 – ₹28,000

Require every bidder to state grade and gauge on every fabrication line. “SS work table” is not comparable to “work table, SS 304, 1.2 mm top, 1.0 mm undershelf, welded and polished.” How to write those lines is in how to prepare a commercial kitchen BOQ.

What does a real 1,500 sq ft kitchen budget look like, line by line?

A 1,500 sq ft mid-tier kitchen serving roughly 150 covers at peak across two cuisines lands around ₹48 lakh before GST — about ₹3,220 per square foot, inside the mid-tier band, with equipment at 57.6% of value.

HeadLine itemValue
Cooking6-burner range with oven₹1,80,000
Combi oven, 10 grid₹5,50,000
Chinese range, 2 burner₹1,80,000
Tandoor with exhaust provision₹1,20,000
Two-tank fryer₹1,20,000
Griddle and salamander₹1,10,000
Subtotal₹12,60,000
RefrigerationWalk-in cold room, 8 sq m₹4,20,000
Undercounter chillers × 3₹2,40,000
Upright freezer, 2 door₹1,20,000
Ice machine, 100 kg/day₹1,60,000
Subtotal₹9,40,000
WarewashingHood-type dishwasher₹3,20,000
Water softener and dosing₹60,000
Subtotal₹3,80,000
PreparationPlanetary mixer, 20 litre₹95,000
Food processor and slicer₹1,05,000
Subtotal₹2,00,000
VentilationExhaust hoods, 14 running metres₹3,60,000
Ductwork, fan, make-up air unit₹2,20,000
Fire suppression system₹1,30,000
Subtotal₹7,10,000
FabricationTables, sinks, shelving, racks₹7,20,000
InstallationLabour, connections, levelling₹3,80,000
Project managementCoordination, commissioning, documentation₹2,40,000
Total before GST₹48,30,000

Three things that table shows which a per-square-foot figure hides.

Ventilation costs more than warewashing and preparation combined. At ₹7.1 lakh it is 14.7% of the project, and it is the head most often missing from a first-pass estimate entirely.

One combi oven is 11% of the whole kitchen. That single line justifies interrogating utilisation hard. If the operation genuinely runs it, it repays through consistency and energy. If it will run twice a day, a 6-grid unit frees ₹2 lakh for elsewhere.

Fabrication at ₹7.2 lakh is where substitution happens quietly. That figure assumes SS 304 at 1.2 mm on food-contact surfaces. A bidder quoting SS 202 delivers the same scope near ₹5 lakh and shows you a ₹2.2 lakh saving you will repay in a replacement.

Add GST at the applicable rate, the excluded items in the next section, and a contingency — 7–10% on a fully frozen design, 12–15% where it is not. Contingency is not padding; it is the honest price of remaining uncertainty.

What nine costs do buyers leave out of a first estimate?

Nine costs are routinely missed: ductwork above the hood collar, make-up air, terrace and structural works, gas bank and piping, electrical upgrade, water treatment, small wares, statutory approval costs, and freight. Together they commonly add 15–25% to a first-pass budget.

Ductwork above the hood collar. Quotations frequently price the hood and stop at the collar. The run to the shaft, the vertical riser, the fan, the acoustic enclosure and the terminal discharge are separate — and on a multi-storey building, substantial.

Make-up air. Extracting air without replacing it puts the kitchen into negative pressure. Doors become hard to open, burners lift, extraction performance collapses, and conditioned air gets pulled from the dining room.

Terrace and structural works. Fan platforms, duct supports, waterproofing penetrations, and structural strengthening for island hoods — which with ductwork can exceed 400 kg.

Gas bank and piping. The LPG manifold, its enclosure, pipe run, isolation valves, leak detection and the exhaust-fan interlock. Safety-critical and not a place to economise.

Electrical upgrade. A commercial kitchen commonly carries 60–130 watts per square foot of connected load depending on whether cooking is gas or electric. If the incoming supply cannot carry it, the upgrade — transformer, cabling, panel — is a base building cost appearing nowhere in your kitchen quotation.

Water treatment. Combi ovens, ice machines and dishwashers need treated water. Hard water destroys boilers and elements faster than any other single factor. Cheap at installation, expensive to retrofit.

Small wares. Pots, pans, GN containers, knives, chinaware, cutlery, chemicals. Commonly 5–8% of kitchen budget, and it falls between the project line and the operations line.

Statutory approvals. Fire NOC processing, FSSAI licensing, trade licence, pollution clearance where applicable, plus liaison costs. The full list is in commercial kitchen licences and approvals in India.

Freight and clearance. Imported equipment carries freight, insurance, customs duty, clearing and inland transport. Confirm whether your quotation is ex-works, CIF or delivered to site — the difference is material. See commercial kitchen equipment procurement.

What four factors move the final number most?

The four biggest drivers are equipment origin, stainless fabrication grade, covers-per-hour target, and how much civil and MEP rework the site requires.

Fabrication grade is the one buyers least often realise is a lever at all. A quote that does not specify which grade applies to which section is a quote where the variable has not been decided, not one where it has been optimised.

Covers-per-hour is the other underappreciated driver, and the more expensive one to get wrong. A kitchen sized for 150 covers costs less than one sized for 400 at identical floor area, because equipment capacity — not square footage — drives most line-item cost. Over-specification is the most common and most costly error in this business, and it only becomes visible once the kitchen is built. Commercial kitchen capacity planning by covers walks through sizing this before quotes are requested.

Site condition is the quietest of the four. A greenfield kitchen designed around the equipment from day one will almost always cost less per square foot than a retrofit into an existing basement with limited exhaust risers — and the gap is in civil and MEP rework, not equipment. MEP coordination in commercial kitchen planning covers what has to reconcile before anything is ordered.

Should I get a lump-sum quote or an itemised BOQ?

An itemised bill of quantities should always sit underneath any lump-sum figure. It is the only way to verify what a total includes, and the only reference point available when a change request arises mid-project.

Ask every shortlisted contractor for the BOQ specifically, not just the total. A contractor unwilling or unable to produce one is giving you a number with nothing to check it against. Deciding who belongs on that shortlist in the first place is covered in how to choose a commercial kitchen contractor. Three structures exist in this market:

Lump sum against a frozen BOQ. The contractor carries quantity risk. Best where design is resolved. Variations priced separately at agreed rates. This is what I recommend for most hospitality projects — it puts the risk with the party who has the expertise to manage it.

Item rate. You pay per item at agreed rates, quantities measured on completion. Useful when scope is still moving, but requires disciplined measurement.

Cost plus fee. Documented cost plus an agreed percentage. Transparent, but only workable with genuine open-book accounting and a contractor you already trust.

Whichever structure, agree the variation rate schedule at signature rather than negotiating each change on its own merits mid-project. What belongs in a commercial kitchen contract and scope of work sets out the clauses.

How does timeline pressure affect cost?

Compressed timelines raise cost by forcing expedited freight on imported equipment, overtime rates on installation, and less room to negotiate supplier pricing. A rushed project frequently costs more than identical scope delivered on a normal schedule.

The arithmetic is straightforward. Imported combi ovens and specialised refrigeration carry six to ten week manufacturing and shipping windows on their own. A kitchen promised in eight weeks that needs them is either air-freighting at multiples of sea freight cost, or it is going to miss. Typical commercial kitchen project timeline covers realistic scheduling by stage.

Ventilation in particular has cost consequences tied to timing. Duct routing decided early, alongside commercial kitchen space planning, avoids the late-stage rework that comes from discovering a conflict after equipment is ordered.

What does a commercial kitchen cost to run?

Beyond capital, budget for energy, water, maintenance and consumables. Energy is the largest, and equipment selected at specification stage sets that consumption for the next decade.

Energy. Induction transfers heat to the pan far more efficiently than open gas flame, which also reduces extraction volume and therefore the conditioning load on the whole space. Condensing hoods, variable-speed exhaust fans and correctly sized refrigeration all repay. See energy efficiency in commercial kitchen equipment and the fuel comparison in commercial cooking range types.

Maintenance. Budget an AMC from year one. Preventive work on hoods, ducts, condensers and steam generators decides whether equipment reaches design life or fails at half of it. What a contract should cover is in commercial kitchen equipment warranty and AMC, and the economics in lifespan of commercial kitchen equipment.

Replacement cycle. Categories age differently. Heavy fabrication and well-maintained cooking equipment outlast high-cycle items like wash arms, fryer elements and door gaskets by years. Budget a rolling provision rather than facing one large refit — when to upgrade commercial kitchen equipment sets out the triggers.

How do I reduce cost without compromising the kitchen?

Reduce through right-sizing capacity, consolidating equipment functions, shortening service runs at planning stage, and phasing genuinely non-critical items. Do not reduce through stainless grade, ventilation capacity, fire suppression, or commissioning.

Five reductions worth making:

  1. Right-size to real peak throughput. The single largest available saving on most projects.
  2. Consolidate functions. One combi can replace a convection oven, a steamer and part of a range — less connected load, less extraction, less floor area.
  3. Shorten service runs at planning stage. Siting the kitchen near the existing shaft, gas bank and incoming panel saves more than any equipment negotiation, costs nothing if decided early, and cannot be changed later.
  4. Phase non-critical items. Secondary prep, additional holding equipment and some small wares can follow after opening.
  5. Match origin to duty. European where the duty cycle is punishing and precision matters; domestic where demand is mechanical and simple.

Five I would refuse:

  1. Stainless below SS 304 on food-contact surfaces. You will replace it.
  2. Undersized ventilation. Every consequence is operational and permanent.
  3. Uncertified fire suppression. Your fire NOC depends on it, and so does the building.
  4. Skipping commissioning. It is the only stage that proves the kitchen works as a system.
  5. Unauthorised sourcing. The warranty and parts chain is worth more than the discount.

Want a real number for your specific project?

Share your covers-per-hour target, layout and menu. We price against an itemised BOQ drawn from our full commercial kitchen equipment range, so the figure reflects your site rather than a generic per-square-foot estimate.